Holder Road Resurfacing Project Update

The timeline for completion the Holder Road Resurfacing Project has been updated. Here is the current timeline.

Thursday, May 21, 2020 – Advertisement in Newspaper

Thursday, May 28, 2020 – Advertisement

Thursday, June 4, 2020 – Bid Opening

Monday, June 8, 2020 – Council Award

Monday, June 15, 2020 – Contract Documents Sent Out for Signature

Friday, June 26, 2020 – Contracts Signed

Monday, July 20, 2020 – Construction Start

Friday, September 18, 2020 – Substantial Completion (60 Days)

Wednesday, September 30, 2020 – Final Completion